up date,
4 of the 6 doors are installed, the garage fire door and the furnace doors both had to be ordered and they are 6 weeks out been 3 weeks now,
electrical is 96% done, need to have outside lights installed around back sliding door and drop down light for the front door, and a hard wired it smoke & carbon detector upstairs, need to be code compliant
all paint has been done downstairs and garage, now working on all trim work, and painting what doors that have been installed, need to pick out door handles yet, insurance company told us to clean them, that's not gonna to work,
plumber is complete done with everything he needed to due,
now we need to start looking at carpet, not yet but soon, will wait 3 more weeks until the doors are all in and all trim work and paint work is completed,
clean out of the back yard its finally time cut the grass and all, have landscape company coming to grade the front and side for now, and replace the stones. Carls fencing is coming in the next 3 weeks to install the new fence and gates as well as the railing for the front steps, that will complete the rt side of the yard for now, still want to put some bushes in but they will need to wait until next year,
then we move on the the driveway and garage floor, and left side of the yard, figure 2 more months it should all be done completely,
then the really fun stuff happens, shopping for furniture.. thank god its not much,